In connection with an electrolyzer system being built by HyAxiom, Inc. for a hydrogen production project on Jeju Island, KraftPowercon has been selected to supply a 5 MW-class rectifier system delivering controlled DC power from the medium-voltage grid interface to the electrolysis process. The delivery is built around KraftPowercon’s H2Kraft concept, a containerized, plug-and-play power conversion solution designed to simplify installation and support efficient commissioning.
Electrolyzers are DC machines in an AC world. The rectifier becomes the bridge, converting incoming AC into stable, controllable DC current for the electrolyzer stacks. As projects scale to multi-megawatt levels and multiple electrolyzer units operate in parallel, the demands on current quality increase. Stable DC delivery supports predictable stack operation, while grid-friendly behavior reduces the risk of disturbance to surrounding grid infrastructure.
Jeju adds another layer. With high renewable penetration, grid characteristics can vary, making harmonic performance and controllability central to stable hydrogen production.
From HyAxiom’s perspective, system-level reliability was a primary consideration.
Censy Thomas - PSCS IPD Lead and Principal Electrical Engineer at HyAxiom
For the Jeju project, KraftPowercon will supply a rectifier system for HyAxiom’s electrolyzer system based on an active front end architecture within its I-Kraft platform, developed to reduce harmonic current contribution and support a cleaner grid footprint. A target of total harmonic distortion in current below 3 percent aligns with expectations that typically apply as plant power levels increase.
Just as important is on-site execution. H2Kraft is designed as a standardized container concept supporting a plug-and-play approach. By reducing installation complexity and enabling a straightforward electrical layout, the solution is intended to help project teams move efficiently from delivery to commissioning, with fewer site interfaces to manage.
Censy Thomas - PSCS IPD Lead and Principal Electrical Engineer at HyAxiom
In Korea, permitting and inspection requirements can become schedule-critical if not addressed early. KraftPowercon supported technical clarification, documentation alignment and KESCO-related inspection readiness as part of its delivery approach, aiming to reduce approval uncertainty and protect commissioning timelines.
Siyul Kim - Senior Asia Application Manager, High Current
In December 2025, HyAxiom confirmed KraftPowercon as the awarded rectifier provider for its 5 MW electrolyzer system for the Jeju hydrogen plant.
Johan Burgren - Sales Director HV & H2 at KraftPowercon
As Korea moves from demonstrations toward repeatable industrial hydrogen assets, the electrical backbone of electrolysis is gaining attention. Solutions must combine grid performance with stack stability while reducing execution risk on site.
With Jeju Island as a proving ground, the project signals a broader shift in the market. As hydrogen projects scale, the role of robust power conversion becomes increasingly central — ensuring predictable operation, compliance with local requirements, and support for industrial-scale hydrogen production.
Censy Thomas - PSCS IPD Lead and Principal Electrical Engineer at HyAxiom.